New Campus Weekly Updates

The new campus is undergoing massive transformation. Each week, this page will be updated to show the progress on specific new campus projects.

Week of November 21

Here are a few of the most recent updates from our campus visit on November 21.

  • The main entrances of the school are undergoing final touches. Basic landscaping has been completed.
  • The soundproofing panels in the Auditorium are being installed. The elevator lift on the stage is complete. 
  • The main Reception area is complete.
  • The Early Childhood playground area is ready for soft flooring to be installed.
  • The tennis courts are in the process of being built. The fencing and the lights have been installed. 
  • The soccer field is complete. The lights and goals have been installed. The running track around the field will be started soon.
  • The swimming pool and training pool are complete, including the viewing area which is located in the Athletics Complex.
  • The safety rail around the indoor walking track, located in the Athletics Complex, has been installed. 
  • The aerobics room, squash courts, and weight lifting areas are undergoing final touches. 
  • The Central Office areas, including the Board Rooms, are almost complete.
  • The soundproofing panels in the Choir Room have been installed. 

Check back next week for a new round of updates on these projects!

Week of October 21

Here are a few of the most recent updates from our campus visit on October 22.

  • The electricity is fully-functioning and the school is no longer running on generators. 
  • The main entrances of the school are almost complete. Basic landscaping has been completed and the parking spaces have been marked off.
  • The Elementary School library has been painted and the flooring should be installed soon.
  • The turf is currently being installed on the soccer field. 
  • The Early Childhood playground area is ready for the final layer of concrete. In the next couple days, the soft flooring will be installed. 
  • The Elementary School mini-gym is awaiting final touches. The basketball hoops are currently being installed. The flooring has been installed.

Check back next week for a new round of updates on these projects!

Week of October 14

After visiting the school on October 15, it is clear that progress is being made each day.

  • The main gym, which is located in the Athletics Complex, has the first few layers of flooring down and is waiting on the final layer of flooring to be installed. 
  • Both swimming pools are tiled and the surrounding areas are undergoing some final touches. Once construction in this area is complete, a scoreboard and touchpads, which will time the laps of swimmers, will be installed.
  • The soccer field has been leveled and is now ready for turf to be installed. Stadium-style lights have been installed and tested. The running track and tennis courts are leveled and awaiting final touches.
  • The indoor/outdoor atrium areas inside the school are almost finished. The turf has been installed.
  • The Elementary School field is almost complete. 
  • The new Early Childhood playground equipment has been installed. The next step is to pour the concrete foundation around this area. After this is done, flooring will be installed. 

Check back next week for a new round of updates on these projects!